Boiler replacements announced for NYCHA

Boiler replacements announced for NYCHA

$200 million plan by 2022

“We’re coming to the table with real resources,” said Mayor Bill de Blasio.
“We’re coming to the table with real resources,”
said Mayor Bill de Blasio.

Mayor Bill de Blasio announced a $200 million investment to replace boilers and upgrade heating systems at 20 NYCHA developments by 2022.

Aimed at NYCHA sites with the most chronic heat and hot water outages, the program will be used to replace aging boilers and modernize heating controls and is expected to benefit about 45,000 residents.

The upgrades are also expected to help NYCHA save about $5 million annually in heating costs.

“Like our investment to replace aging roofs, this commitment to new heating systems cuts right to the heart of the biggest problems NYCHA residents face, and will make a difference thousands of them will feel,” said de Blasio. “The record-setting cold this winter has hit these aging boilers and pipes hard. We’re coming to the table with real resources to attack these problems, and urge our federal and state partners to do the same.”

De Blasio has committed $2.1 billion to NYCHA’s capital infrastructure from fiscal year 2014 to fiscal year 2027 and $1.6 billion to the agency’s operations from fiscal year 2014 to fiscal year 2022.

“I applaud Mayor de Blasio for stepping up and making NYCHA residents a priority. $200 Million in capital investments to address the heating issues in some of the most problematic developments is much needed, especially during a time of decreased funding from the federal government,” said Councilmember Alicka Ampry-Samuel, Chair of the Committee on Public Housing. “While the city is finding ways to fund NYCHA’s boiler and heating crisis, I call on our state colleagues to push the Governor for additional funding to address this never ending emergency.”

The project will bring about the replacement of at least 39 boilers, and install new heating controls at 15 sites to regulate boiler temperature.

It will also modernize systems by separating hot water from the heating boilers to reduce strain and decrease the likelihood that tenants would simultaneously lose heat and hot water during outages.
The following NYCHA developments will receive upgrades: Morris I, Morris II, Taft, Cypress Hills, Farragut, Sotomayor Houses, Rangel, Fiorentino Plaza, Long Island Baptist Houses, Robinson, Astoria, Baruch Houses Addition, Baruch, McKinley, Melrose, Pelham Parkway, Pomonok, Rutland Towers, Soundview and South Beach.

Still, not everyone offered praise for the city’s announcement.

“Mayor de Blasio’s announcement today is cold comfort for the tenants of NYCHA, as it does nothing to accelerate the timeline of the procurement process. Even on the most optimistic schedule the city will have a different mayor when these new boiler installations are completed,” said Bronx Borough President Rubén Díaz Jr. in a statement. “We cannot afford to wait any longer to make critical, long overdue repairs. NYCHA must issue an emergency declaration and take the necessary steps to cut through the red tape of the procurement process and replace broken boilers faster. This heat crisis is a dire health emergency, and it requires an immediate, permanent solution.”

The upgrades are also expected to help NYCHA save about $5 million annually in heating costs.
The upgrades are also expected to help NYCHA
save about $5 million annually in heating costs.

“We are glad to see that Mayor de Blasio has increased his original stated investment of $13 million to $200 million for updated boilers. However, given the gravity of the city’s heating crisis, a more profound investment is needed,” said Afua Atta-Mensah, Esq., the Executive Director of Community Voices Heard, a social justice advocacy group. “NYCHA has 326 developments, the mayor’s most recent investment will serve 20 developments. What will happen to the residents of the other 306?”

“New Yorkers cannot afford to wait until 2019 to see their heating systems repaired and modernized. We need to cut through the red tape and speed up the repair process this year,” Atta-Mensah added. “NYCHA has said they need $2 billion to see every development receive necessary upgrades. We want to see a realistic timeline that helps to meet those immediate needs. Every New Yorker deserves to sleep in a warm home.”

 

Related Articles

Back to top button

Adblock Detected

Please consider supporting us by disabling your ad blocker